Client Context

A major Singapore commercial and retail development with a peak electrical demand exceeding 1,200 kVA sought to reduce its SP Group Maximum Demand (MD) billing and prepare for BCA Green Mark recertification. The facility operates 18 hours per day, with peak demand concentrated in the 09:00–21:00 window, resulting in significant MD charge liability under Singapore's commercial electricity tariff.

Challenge

The client required a BESS solution that: (1) delivered measurable MD reduction under Singapore's electricity tariff structure; (2) met BCA Green Mark documentation requirements; (3) could be installed within the existing plant room space without structural modification; and (4) was certified to Singapore Fire Safety Act requirements for battery energy storage in commercial buildings.

LHS Electronics Solution
Juhang liquid-cooled

2 × 500 kWh Juhang liquid-cooled ISO container modules (1 MWh total) installed in the basement plant room

AI EMS

Configured for Singapore SP Group tariff-optimised discharge scheduling: charge during off-peak, discharge during peak billing windows

Hirschmann

Managed switches providing the IEC 61850 data communication backbone between BESS BMS, building EMS, and the facility's existing SCADA

KLG Smartec

IEC 61850 gateway connecting the Juhang EMS to the facility's power monitoring SCADA

Belden

Belden shielded instrumentation cable throughout the BESS communications wiring

Integration

Full commissioning, staff training, and 24/7 remote monitoring integration

Outcome